Ovia, Edo State – March 03, 2025
Eastlake Exploration and Production Limited (“Eastlake”), jointly with OML 96 Asset Operator – Dubri Oil Company Limited (“DOCL”) has completed the Geomatics Survey in preparation for the commencement of Ovia-2 and Ovia-3 drilling campaign. The survey was conducted by the experienced team of Startfix Geosolutions Services Limited with a particular focus on accuracy and adherence to industry standards. The scope of work covered the following:
– Setting out the Ovia-2 and Ovia-3 blue pegs
– Setting out of boundaries for Ovia-2 and Ovia-3 well locations
– Detailed survey and grid levelling of Ovia-2 and Ovia-3 well locations
– Setting out and grid levelling of flowline boundaries Right-of-Way for product evacuation
At Eastlake, the priority is to ensure that all activities are conducted in a manner that prioritizes the excellence, professionalism and delivery of set goals to ensure that employees, contractors, stakeholders, and the communities in which we operate in, are mutually satisfied.